Power |
To get the
power sanction first one should approach the respective sub-divisions under whose
jurisdiction the industry falls, with the following documents:
|
If the
shed comes under KIADB/KSSIDC administered layouts, then the allotment letter is a must
along with the other documents mentioned below.
Application
form in the prescribed format mentioning the required load and the type of industry.
For sheds
other than those which come under the jurisdiction of KIADB/KSSIDC , license from the
corporation or municipality, under whose jurisdiction it falls, has to be produced.
Khata
certificate
Latest tax
paid receipt.
NOC (no
objection certificate) from the owner of the building taking responsibility for the
arrears to be cleared if any.
If the
power requirement is below 67 HP, it will be provided on LT (low tension) basis.
Tariff
would depend on the purpose and the requisition load.
The party
has to pay the following deposits.
1. 3 months minimum deposit which depends on the load required.
2. Rs.980/- has to be paid as meter security deposit. For single phase meter and load less
than 5 kW. Rs.4,900 has to be paid if the load required is between 5 to 25 LW, and for the
load above 5 kW Rs.15,070.00 has to be paid as meter security deposit.
3. Rs. 150/- has to be paid by all towards supervision charges.
4. Infrastructure charges depend on the load requirement.
In case of
any delay/grievances one can approach KERC (Karnataka electricity regulatory commission)
|